The US 550/I-25 project completion has been delayed until late December. The original completion date was scheduled for the first week of November. The contractor, FNF Construction, has cited numerous reasons for the delays, including utility conflicts and difficulties with traffic control and phasing. They are currently negotiating with the NMDOT the amount of fines that will be levied against them because of the delayed completion.
-